Expansion of the CLIP Intermodal Terminal

Jasin

2021
At this stage of works, the construction of the southern terminal plate along with the road and track system will be continued. A total of 7 km of new tracks will be built, including 15 turnouts. The surface area of the reinforced concrete terminal slab will be as much as 28,620 m2. 4.5 km of overhead line networks will also be built. The scope of works also includes the removal of system and field clashes (electricity, telecommunication and drainage clashes, as well as those related to the need to build engineering facilities) and the construction of accompanying infrastructure elements, e.g. the overhead line network, telecommunication and electricity duct systems and drainage system, construction of railway scales.
Grupa NDI General Contractor Grupa NDI
Centrum Logistyczno Inwestycyjne Poznań II Investor Centrum Logistyczno Inwestycyjne Poznań II
2021 Project's execution 2021