Modernization of the tram network

The renovation of the track and catenary line will cover an almost 14-kilometre section from Fieldorfa-Nila Street to the loop at Pokoju Avenue. The investment will be carried out in the design and build formula. The contract value is 114.5 million PLN.
The modernization of the trackway and the contact line will cover a section of almost 14 km, from Fieldorf-Nil street to the loop at al. Pokoju. The investment will be implemented in the design and build formula. The value of the contract is 114.5 million zlotys.
NDI/Balzola Consortium General Contractor NDI/Balzola Consortium
MPK Częstochowa Investor MPK Częstochowa
2018-2021 Project's execution 2018-2021